Construction of Pedestrian Bridge (JPO) at KM 7 + 200

Construction of Pedestrian Bridge (JPO) at KM 7 + 200

11 May 2017
Author: Administrator

At the end of May 2017, the construction of Pedestrian Bridge (JPO) in KM 7 + 200 finally was completed. In order to expedite the development process, the BSD toll was conducted temporary road closure for 6 hours starting Thursday, 11 May 2017 at 11PM until Friday, 12 May 2017 at 05.00 AM, in order to install the bridge stretch (girder).
 
Related to the road closure, BSD Toll Management was informed to Toll Road users about the installation. The information was announced through all of social media, Twitter and Facebook, and installed banner since of Monday 08 May 2017. Management of BSD Toll was also coordinated with all related institutions to informed alternative road that can be used during girder installation.